Amphitheater Waterproofing Rehabilitation - Cesar Chavez Student Center

   
Construction Dates

2009-2010 (completed)

Description
Bigger image of Cesar Chavez building image open in new window

The project replaces the substrate and waterproofs the Cesar Chavez Student Center amphitheater (north pyramid), including removal and re-installation of the existing pre-cast concrete seats.

Scope of work

Removal of the existing waterproofing and installation of a liquid hot rubberized, asphalt, fully reinforced waterproofing system to cover all surfaces below the existing pre-cast concrete seats and repair of deteriorated surfaces.